| Technical Infrastructure |
Below you find selected references from the field of Technical Infrastructure.
|
|
|
| |
|
|
| . |
. |
. |
| |
|
District heating in Gropiusstadt
The district heating network in Gropiusstadt is being modernised step by step in the next 10 years. BLS Energieplan was commissioned by GbR Fernheizung Gropiusstadt and respectively RWE Innogy to carry out the planning and construction management of this project. Nominal diameters: DN 65 to DN 600. |
| Services |
Modernisation of approx. 2,000m as 3-conductor system while not affecting heat supply. |
| Client |
GbR Fernwärme Gropiusstadt/RWE Innogy |
| Place / Period |
Berlin / 2005 - 2012 |
|
| |
|
|
| . |
. |
. |
| |
|
District heating network in Garching
BLS Energieplan GmbH was comissioned by AR Recycling GmbH to carry out the planning for developing a district heating network not far from the major airport Franz Josef Strauss and connecting the city of Garching, the Technical University of Munich and different commercial buildings. The project has a construction time of 5 years. The energy to be distributed via the district heating network will largely be generated by renewable energy sources, such as geothermal energy. |
| Client |
AR Recycling GmbH |
| Place / Period |
Garching/Hochbrück / 2007until 2012 |
|
| |
|
|
| . |
. |
. |
| |
|
Connecting supply facilities to the East Terminal at Tegel Airport
Planning and construction management of linking and connecting an airport terminal to all supply facilities. |
| Services |
Planning and construction management of all trades |
| Client |
Berliner Flughafen-Gesellschaft mbH |
| Place / Period |
Berlin 2006 |
|
| |
|
|
| . |
. |
. |
| |
|
Modernisation concept of district heating pipeline in Gropiusstadt
The condition of the district heating network is being assessed and evalulated after more than 40 years in operation for an area of 40,000 flats. Based on this evaluation, a modernisation concept will be developed for the coming years. |
| Client |
GbR Fernwärme Gropiusstadt |
| Place / Period |
Berlin / 2006 |
|
| |
|
|
| . |
. |
. |
| |
|
Transport route in Hönow
1.8km route to transport district heat (DN 250) and transfer station of 15MW for supplying heat to approx. 1,000 double and single-family houses in the development area of Hönow. |
| Services |
Planning and construction supervision |
| Client |
Harpen EKT |
| Place / Period |
Hönow / Berlin / 2005 - 2006 |
|
| |
|
|
| . |
. |
. |
| |
|
Basic automation and special systems for
SW Eisenhüttenstadt
Electrical engineering/measurement and control; retrofitting of a total of 145 heat generation and heat transfer systems (boiler plants, district heating transfer stations).
Services:
- Retrofitting of measurement, control and electrical engineering of the systems
- Basic automation (switch cabinets, control and regulation) of the systems
- Remote data transmission and process visualisation system (PVS) for monitoring and operating the systems with bidirectional data acquisition
- M-bus data transmission system for remote outputs of the heat meter data integrated into the PVS and data transmission to the consumption and invoice department
- Text message sent as part of fault message management system for monitoring the systems |
| Client |
Stadtwerke Eisenhüttenstadt GmbH |
| Place / Period |
Eisenhüttenstadt / 2004 until 2005 |
|
| |
|
|
| . |
. |
. |
| |
|
District heating network in Berlin-Neukölln
Planning of a district heating pipeline (DN 600) with a length of 5.5km crossing the Teltow canal and the federal motorway twice for connecting the newly constructed CHP plant to the district heating network of Berlin, Gropiusstadt. |
| Services |
Technical planning of the site |
| Client |
Harpen EKT |
| Place / Period |
Berlin / 2002 until 2003 |
|
| |
|
|
| . |
. |
. |
| |
|
District heating network for Harpen / BTB
Planning of a network connection pipeline (DN 300) with a length of 1.5km for the hydraulic connection of two heat supply areas. |
| Services |
Planning and construction management |
| Client |
Harpen EKT GmbH |
| Place / Period |
Berlin / 2002 |
|
| |
|
|
| . |
. |
. |
| |
|
Cooling network Place de l’Europe, Luxembourg
Planning and implementation of a cooling network with a route length of 1,500m and nominal diameters of 125 to 450. The cooling capacity to be transferred totals 7.5MW. |
| Services |
Work phases 1 to 8 |
| Client |
LuxEnergie |
| Place / Period |
Luxemburg / 2001 until 2006 |
|
| |
|
|
| . |
. |
. |
| |
|
Hansacom network node, Greifswald (Mecklenburg Western-Pomerania)
Set up and connection of 2 network nodes in the optical fibre network of the regional city carrier Hansacom GmbH in the urban area of the Hanseatic City of Greifswald. |
| Services |
Engineering of all work phases, ventilation and air conditioning, electrical engineering, reserve power supply, cooling. |
| Client |
Hansacom GmbH Greifswald |
| Place / Period |
Greifswald / 2001 |
|
| |
|
|
| . |
. |
. |
| |
|
Hansacom optical fibre network, Greifswald (Mecklenburg-Western Pomerania)
Realisation of an optical fibre connection including outgoing sections between the network node CHP plant old town and the multipurpose swimming pool Greifswald with the aim of closing an optical fibre ring with deviations and connections to the central unit of the regional city carrier Hansacom GmbH in the Hanseatic City of Greifswald. |
| Services |
Engineering of all work phases, civil engineering works, conduit laying, optical fibre cable pulling and connection. |
| Client |
Hansacom GmbH Greifswald |
| Place / Period |
Greifswald / 2000 until 2001 |
|
| |
|
|
| . |
. |
. |
| |
|
Hansacom colocation centre, Greifswald (Mecklenburg-Western Pomerania)
Set up of the administration and data centre of the regional city carrier Hansacom GmbH in the Hanseatic City of Greifswald. |
| Services |
Engineering of all work phases, electrical engineering, reserve power supply (battery system and emergency power system), cooling, ventilation and air conditioning, double floor construction, lightning protection and earthing, control systems. |
| Client |
Hansacom GmbH Greifswald |
| Place / Period |
Greifswald / 2000 until 2001 |
|
| |
|
|
| . |
. |
. |
| |
|
BEWAGE heat control room, Berlin
Joining of two control rooms (East and West) on one site to monitor the district heating network and transfer stations of the utility company BEWAG in Berlin. |
| Services |
Planning and construction management |
| Client |
BEWAG Berlin |
| Place / Period |
Berlin / 2000 until 2001 |
|
| |
|
|
| . |
. |
. |
| |
|
District heating network in Kirchberg, Luxembourg
Planning of the district heating pipeline for the Kirchberg development area with a connected load of approx. 100MW and ca. 80 transfer stations. |
| Services |
Technical planning of the site |
| Client |
Ville de Luxembourg / Fonds de Kirchberg |
| Place / Period |
Luxemburg / 1997 until 2007 |
|
| |
|
|
| . |
. |
. |
| |
|
Local heating network in Berlin-Pankow, Schillerstraße
Local heating network to supply a residential area with 200 residential units. |
| Services |
Technical planning of the site and construction supervision |
| Client |
Deutsche Kohle Marketing GmbH |
| Place / Period |
Berlin / 1996 until 2005 |
|
| |
|
|
| . |
. |
. |
| |
|
Local heating network of Hönow
Laying of 9km district heating pipeline (dimensions: DN 50 - DN 250) in a development area including 200 transfer stations. |
| Services |
Planning and construction supervision of all trades |
| Client |
Deutsche Kohle Marketing GmbH |
| Place / Period |
Berlin / 1996 until 2005 |
|
| |
|
|
| . |
. |
. |
| . |
|
|
| |
|
|