of Biomass.

   
 
. . .
   

Rapeseed oil combined heat and power generation plant, Twistringen
Construction of a combined heat and power generation plant fuelled by rapeseed oil. Provision of process heat and process steam. Electrical capacity of 500kW.

Services Planning phases 2 to 8 of the HOAI (German fee regulation for architects and engineers)
Client Raiffeisen-Warengenossenschaft Twistringen eG
Place / Period Twistringen / 2005
 
. . .
   

Wood-fired hot water systems in Flöha, Limbach-Oberfrohna, Schöneck and Hohenstein, Saxony
Planning of 4 boiler plants incl. associated trades at 4 different sites with a capacity ranging from 1,500 to 2,000kW to provide the base heating load for the existing heat supply systems, fuel A1 and A2 and natural-finish wood.

Client Harpen EKT
Place / Period Flöha, Limbach-Oberfrohna, Schöneck and Hohenstein / 2004 bis 2005
 
. . .
   

Pellet-fuelled heat generation, Berlin-Reinickendorf
Planning and construction supervision of a pellet and gas-fuelled central heating plant (pellet boiler of 450kW and gas boiler of 1,400kW) including local heating network and transfer stations for supplying heat to a residential area.

Client Baugenossenschaft Reinickes Hof
Place / Period Berlin-Reinickendorf / 2004 until 2005
 
. . .
   

Wood-fired boiler plant for the hospital Treuenbrietzen, Brandenburg
Planning of a wood-fired boiler plant (incl. associated trades) of 1,600kW to supply the hospital complex of Treuenbrietzen.

Client Johanniter-Hospital in Fläming gGmbH
Place / Period Treuenbrietzen / 2002 until 2003
 
. . .
   

Biomass-fuelled CHP plant Berlin-Neukölln
Construction of a gas-fired boiler house with a thermal capacity of 130MW as well as whole approval procedures for the gas-fired boiler house and the biomass-fuelled CHP plant (thermal capacity of 60MW, electrical capacity of 20MW).

Services Engineering of work phases 2 to 7 and controlling
Client Harpen EKT
Place / Period Berlin / 2002 until 2003
 
. . .
   

Biomass power plant in Eberswalde
Approval planning of a biomass power plant in Eberswalde according to the 17th German Federal Emission Control Regulation, power generation of 20MW, fluidised bed combustion.

Services Approval planning
Client Babcock Borsig Power Environment GmbH
Place / Period Eberswalde / 2001 until 2002
 
. . .
.  
 
 
^
 